Pool models, construction conditions and care to help you plan your project.
In this guide 4
Project note: The base thickness, concrete class, reinforcement, excavation allowance, pipe diameter and quantities given in this guide are preliminary planning examples; they are not a structural design that can be applied to every site. The design must be prepared by a qualified engineer after assessing the geotechnical investigation, groundwater, loads and local regulations. A full pool can also be affected by external hydrostatic pressure; draining, drainage and electrical work require expert supervision.
For villa owners considering ordering a pool from Turkey to Georgia, the biggest question marks are whether cross border logistics is complicated, whether there will be waiting at customs, and whether the products will arrive undamaged. Barut Prefabrik Havuz Sistemleri Ltd. Sti., operating under the Sermed Havuz brand, routes the delivery trucks leaving its factory in Duzce Cumayeri along the Black Sea coastal route to the Sarp Border Crossing (Sarpi). With the support of a customs broker and the Batumi office, the targeted delivery time is typically a few working days from order confirmation; the durations below are example values for planning purposes and may vary with traffic volume, the season, the customs processing load and weather conditions.
Palletized prefabricated pool kits leaving the Duzce Cumayeri factory by truck reach the Sarp Border Crossing via the Black Sea coastal road. In an example scenario for planning purposes, the route is approximately 950 km and around 16 hours of uninterrupted driving, entry registration procedures take 12 to 24 hours, and total delivery is projected at approximately 4 to 5 working days from order confirmation. These durations are not a commitment but a typical planning assumption; delivery can be made door to door to the villa site in Batumi, Gonio, Kobuleti or Chakvi.
Cross border construction is less about distance than about the discipline of logistics planning. In practice, the Duzce factory is a nearby production base for Batumi projects.
01. The Duzce to Sarp to Batumi Road Corridor and the Strength of Fast Transit
Three advantages provided by this logistics route:
- Uninterrupted Road Connection: Direct truck transport without transfers can be planned along the Black Sea coastal road.
- Short Distance From Sarp Customs: The Sarp crossing is within tens of kilometres of the villa areas around Gonio and Batumi, and is reached in a short time depending on traffic.
- Compact Packaging: The 20 mm F-Stone fibre cement panels, galvanized steel support elements, liner rolls and the MyBox cabinet are shipped shrink wrapped on industrial pallets.
02. Customs Documents, Conformity Documents and Damage Free Palletizing
The approach to international delivery:
- Export Paperwork: Transport and origin documents together with product declarations are prepared at the factory according to the type of shipment and the regulations in force. Which documents apply is confirmed separately for each shipment; no claim is made here that any particular document or certificate exists.
- Local Stock and Service Support in Batumi: The spare parts support at the Batumi office aims to reduce waiting time on site caused by missing parts.
- Management of the Customs Process: Depending on the requested delivery terms, import and customs procedures can be managed by the Sermed Havuz logistics team; the scope is set out in writing in the contract.
03. Table of Delivery Stages From Order to Site
| Process Stage | Operation and Route | Duration (example planning assumption) |
|---|---|---|
| Factory Production | Duzce Cumayeri panel cutting and liner manufacture | 2 to 3 days |
| Road Transport | Duzce to Sarp Border Crossing (approximately 950 km) | ~16 hours of driving |
| Customs Procedures | Sarp transit and registration approvals | 12 to 24 hours |
| Unloading on Site | Sarp to Batumi, direct delivery to the address | ~2 hours |
| TOTAL DELIVERY | From the Factory to Your Garden Gate | Approximately 4 to 5 working days (may vary) |
Conclusion: Logistics planning makes it possible to set up a shipment programme aligned with the project's construction schedule; exact dates are confirmed at the time of ordering.
Frequently asked questions
How many days does transport from the Duzce factory to a Batumi site take?
Following order confirmation, the typical planning assumption including factory preparation, road transport and customs clearance at Sarp is 4 to 5 working days. Customs congestion, the season and weather conditions can extend this period.
Does the customer pay the customs duties?
The delivery terms are set out in writing in the quotation. An option similar to DDP, where customs duties and transport are on the seller's side, can be offered; in that case the customer does not have to deal with customs bureaucracy. Which costs belong to whom is clarified in the contract.
What happens if a part is broken in transit?
The aim is to keep spare F-Stone panels, profiles and equipment at the Batumi office; a damaged part is replaced as quickly as possible depending on stock availability. Same day replacement cannot be guaranteed in every case.
What is done if the truck cannot pull up to the garden gate?
Pallets unloaded from the truck on the main street are transferred into narrow villa streets using light commercial vehicles or suitable handling equipment. Access conditions are assessed during the site survey.